            Currently TCP requires TLS 1.0 and 1.1


            Our standard process for a server migration is:-  

            Prep Phase - done prior to the planned date of migration  

                  1) New Server provisioned along side the existing server - Done by the relevant IT support 
                  2) Installation of software on the new server, restoration of a backup to test SQL server setup,permissions and performance. - Approx 60 minutes work  

            Migration Phase - 60 minutes  

                  3) Decommission the system on the old server (remove the software licence, disable the system, take a final backup)  
                  4) Restore the system on the new server
                  5) Switch the new server on to the IP address of the old server - Done by IT
                  6) Commission the system on the new server including final testing  

            Final decommissioning of the old server - Done by the relevant IT support 